Construction work progresses on the Metro North/Atlantic Street Bridge replacement project as two new bridge spans have been installed on the north side of the bridge. The spans will carry Tracks #1 & #3 after new railroad ties, tracks and ballast are in place. The final two spans for the north side are scheduled to be rolled into place and these will carry Track #5 and the new Track #7. Earlier this week, two bridge spans were installed on the south side of the bridge with train service restored to Tracks #2 & #4.