Metro North/Atlantic Street Bridge Public Info Update Session, Thursday, June 20, 2019

By |

Metro North/Atlantic Street Bridge Public Info Update Session, Thursday, June 20, 2019

Public Info Session, Thursday, June 20, 2019, 6pm Residents, commuters, business owners and other interested individuals are invited to attend the public information session for an update on the project progress and to learn more about the bridge roll in schedule, impacting intermittent road closures, detours, pedestrian detours and special Metro North service bulletins starting…

Read more »

Special Metro North Construction Timetable to be in Effect During Metro North/Atlantic Street Bridge Roll In Operation; Metro North Construction Timetable now available

By |

Special Metro North Construction Timetable to be in Effect During Metro North/Atlantic Street Bridge Roll In Operation; Metro North Construction Timetable now available

Starting June 28, 2019-July 7, 2019, the new Metro North/Atlantic Street Replacement Bridge will be rolled into place during a 9 day sequenced operation. During the bridge replacement, Metro North train service remains operational with service reductions and a special Metro North Construction timetable just for the roll in period.   The special Metro North…

Read more »

New Metro-North/Atlantic Street Railroad Bridge to be installed starting on/about June 28, 2019 in Stamford

By |

New Metro-North/Atlantic Street Railroad Bridge to be installed starting on/about June 28, 2019 in Stamford

New Metro-North/Atlantic Street Railroad Bridge to be installed; I-95NB Exit 8 & Local Roadway closures with Detours, and Metro North Schedule Changes to be in Effect starting on/about June 28, 2019 in Stamford   The Connecticut Department of Transportation is announcing that temporary closures and detours for I-95 NB Exit 8 Off Ramp and Local…

Read more »

ATTENTION: Atlantic Street Bridge Public Info Session, Thursday, June 20, 6pm

By |

ATTENTION:  Atlantic Street Bridge Public Info Session, Thursday, June 20, 6pm

Residents, commuters, business owners and other interested individuals are invited to attend the public information session for an update on the Atlantic Street Bridge Replacement project and the upcoming bridge roll in taking place June 28-July 8, 2019.  Intermittent road closures, detours and special service bulletins for Metro North will be in effect during the…

Read more »

Atlantic Street Bridge Replacement Project Update Session: Thursday, June 20, 2019 at 6pm

By |

Atlantic Street Bridge Replacement Project Update Session: Thursday, June 20, 2019 at 6pm

Residents, commuters, business owners and other interested individuals are invited to attend the public information session for an update on the project progress and to learn more about the construction activities and impacts that will be taking place starting with the replacement bridge roll in schedule on June 28-July 8, 2019 and the Atlantic Street…

Read more »

Atlantic Street Bridge Superstructure Construction Work Nears Completion with 28 Days to the Bridge Roll In

By |

Atlantic Street Bridge Superstructure Construction Work  Nears Completion with 28 Days to the Bridge Roll In

Stretching across Atlantic Street, between Dock Street and the Metro North/Atlantic Street Bridge, are two bridge spans that are under final construction before being rolled into place in 28 days starting June 28-July 8, 2019. Clearly visible from the train and also from the street level, these two concrete-reinforced steel spans, rest atop temporary trestles….

Read more »

The Countdown Begins! 36 Days Remain Until The New Metro North/Atlantic Street Bridge Is Rolled Into Place

By |

The Countdown Begins! 36 Days Remain Until  The New Metro North/Atlantic Street Bridge Is Rolled Into Place

In 36 days, the Metro North/Atlantic Street Bridge will begin its installation journey to replace the existing bridge that was built more than a century ago. The new bridge is expected to be rolled into place during a 9 day period starting June 28 through July 8, 2019 with intermittent local road closures, detours, pedestrian…

Read more »

SPECIAL NOTICE! The Route 1 Bridge Replacement over I-95 Scheduled for Two Weekends Starting May 31, 2019

By |

SPECIAL NOTICE! The Route 1 Bridge Replacement over I-95  Scheduled for Two Weekends Starting May 31, 2019

To those following the Metro North Railroad/Atlantic Street Bridge project, we have been notified that there will be activity in the area that is unrelated to our project. While this is NOT related to the Metro North Railroad/Atlantic Street Bridge project, we are sharing this information to help get the word out.   The Exit…

Read more »

Metro-North/Atlantic Street Bridge Replacement Project Advances Excavation for Center Pier

By |

Metro-North/Atlantic Street Bridge Replacement Project Advances Excavation for Center Pier

Construction of the new Metro-North/Atlantic Street bridge progresses under the railroad tracks with excavation and drilling piles for the new bridge center pier. Because the new bridge is wider and longer than the existing bridge, a center pier is required to support the new spans. With Atlantic Street remaining closed under the bridge, the construction…

Read more »

Atlantic Street Bridge Replacement Project Utility Relocation Makes Way for the New Track #7

By |

Atlantic Street Bridge Replacement Project Utility Relocation Makes Way for the New Track #7

The new Metro-North/Atlantic Street bridge will carry a new Track #7 to improve railroad operations for Metro North riders. Upon completion, Track #7 will have its own platform which will accommodate 4 stairwells for egress along South State Street, making for more convenient access to sidewalks for commuters.   To create the additional width at…

Read more »