March 25, 2023

Latest:
  • Traffic Alert for South State Street: November 30 - December 31, 2020
  • Atlantic Street Bridge Construction Operations Underway
  • Eversource Energy Company Transmission Work Continues On South State Street
  • Eversource Energy Company Transmission Work Continues On South State Street
  • Eversource Energy Company Transmission Work Continues On South State Street
  • South State Street Traffic Alert
  • Atlantic Street Detour Information for Friday, January 31-Saturday, February 1, 2020
  • Metro North/Atlantic Street Bridge Replacement Project Takes Top Honors For Best ABC Project/Railroad Bridge at December 2019 International Accelerated Bridge Construction Conference
  • Atlantic Street Detour Information for Sunday, November 10, 2019
  • Atlantic Street Officially Re-Opened Under New Metro North/Atlantic Street Bridge; Bridge and Roadway Improvements Completed On Time With Minimal Impacts to Traveling Public

CTDOT Project #s 135-326, 135-301 & 301-163

  • Home
  • Overview
    • Timeline
    • Project Partners
  • Project Updates
    • Press Releases
  • Traffic Alerts
  • FAQ
  • Project Photos
  • Contact Us
Menu

Project Photos

Atlantic Street Re-Opened
Road now opened
North side of Bridge

New pavement marking operation underway
New road markings being installed
New pedestrian sidewalks

Paving Underway
Atlantic Street construction
Island on Atlantic Street

Paving Equipment Staged
New sidewalks under construction
Ballast loading onto new spans

Under south side of new bridge
Construction under new bridge.
Atlantic Street Reconstruction

Excavation advances
Excavation of Atlantic Street
North side of bridge

North side of new bridge
Atlantic Street with new bridge before roadway construction
Two spans rolled in

South side roll in
South Assembly area ready

SPMT’s staged for hauling spans
South staging area
SPMT delivery

Bridge spans at South Assembly Area
Steel delivered for spans
Bridge spans for Tracks 2 & 4 under construction

Steel arrives for bridge spans
Footings excavated at South Assembly Area
South Assembly Area

South Assembly Area
Forming up the footings at South Assembly Area
South Assembly Area Bridge Footings April 3, 2019

Rebar for footings South Assembly Area
South Assembly Area
Trusses arrive at South Assembly Area

 

Decks ready for transport
Two deck spans ready
Concrete poured on spans

Formwork at North Assembly Area
Formwork on North Assembly Area Spans
Bridge Spans and Formwork at North Assembly Area

Bridge decks with formwork
Deck superstructure construction North Assembly Area
Rebar on deck superstructure

Girders at North Assembly Area
Girders form deck superstructure
North Assembly Area Footings and Trusses

Temporary abutment at North Assembly Area
Footings poured and temporary abutments at North Assembly Area
North Assembly Area with footings and trusses

Installing re-bar for bridge deck construction
Footings for bridge superstructure at North Assembly Area
Soil nailing in progress at North Assembly Area.

Stripping Top Soil in North Assembly Area July 2018
Clearing and Grubbing S. State Street at Elm
Removing Top Soil North Assembly Area

North Assembly Area
North Assembly Area
Excavation at North Assembly Area

Four deck spans under construction at North Assembly Area
Caps beams on falsework at North Assembly Area
Cap beams atop falsework at North Assembly Area

Girders arrive at North Assembly Area

Train crossing West Side jump span on Track 4
Train crossing at jump span, west side Track 4
Excavation under tracks, Oct. 2018

Excavation under tracks, East side, Oct. 2018
Excavation under tracks, west side, October 2018
Lagging under West side jump span

Walers and struts under jump span
Excavation under Tracks 4 & 2, West Side
Train tracks line the new jump span.

Track 3 during jump span installation
West span welding, Track 4, Sept. 2018
Track 4 west jump span delivery Aug. 2019

Jump spans are lifted into place.
Track 1 outage to install jump spans, Sept. 2018
Work taking place on Track 5 for jump span installation.

Track 3 Jump Span Install
Metro North running trains on Track 4
Metro North continues service during jump span installation

Micro-piles staged in construction area
Micro pile casings await installation for the new bridge abutments.
Micro-piles will be installed to support the new bridge abutments

Jump spans await installation
Original iron girders under Atlantic Street Bridge
Track shadows on Atlantic Street

Pre-Construction of Jump Spans
Pre-construction of jump spans, taken April 2018
Existing Atlantic Street Bridge under tracks

Fascia Reveal RW 106
Fascia Reveal RW 106
Retaining Wall Fascia Reveal

Retaining Wall 106 April 3, 2019
Concrete Pour RW 106
Retaining Wall Continued Concrete Pours

Monopole #991 Night Work
Monopole #991 Drill rig
Stair A Wall 105

Pre-cast concrete panels form retaining wall
Retaining Wall with Lagging
Retaining Wall lagging Wall 106

Pre-cast concrete lagging forms the new retaining wall.
H-piles rise high for supporting the new retaining wall on S. State Street.
H Piles Wall 106

H Piles Wall 105
Drill Rig on S. State Street at Wall 106
Pile driving along Wall 106 for new retaining wall

Steel H-piles await installation along S. State Street
H-piles are mobilized pre-installation in the drilled shafts

Center Pier Micro Piles Underway
Center Pier excavation
Center Pier excavation

Center Pier pile drilling
Drilling piles for Center Pier
Center Pier SOE Piles

Center Pier Excavation April 3, 2019
Center Pier excavation advances

Pedestrian bridge girders in place at the new Atlantic Street Bridge.
Pedestrian girders installed
North side of Atlantic Street Bridge before girder installation

North side of bridge before girder installation
Formwork on western abutment, north side of bridge
North side of bridge before pedestrian girders installed

Form work on abutment prior to girder installation
Formwork on abutment prior to girder installation
Concrete poured for completed abutment on North Side of bridge

Foundations for new Track #7 platform

South side of Atlantic Street Bridge
South side of Atlantic Street Bridge
South side of Atlantic Street Bridge

2018 All Rights Reserved CTDOT Website Developed by BL Companies
 

Loading Comments...