- Atlantic Street Re-Opened
- Road now opened
- North side of Bridge
- New pavement marking operation underway
- New road markings being installed
- New pedestrian sidewalks
- Paving Underway
- Atlantic Street construction
- Island on Atlantic Street
- Paving Equipment Staged
- New sidewalks under construction
- Ballast loading onto new spans
- Under south side of new bridge
- Construction under new bridge.
- Atlantic Street Reconstruction
- Excavation advances
- Excavation of Atlantic Street
- North side of bridge
- North side of new bridge
- Atlantic Street with new bridge before roadway construction
- Two spans rolled in
- South side roll in
- South Assembly area ready
- SPMT’s staged for hauling spans
- South staging area
- SPMT delivery
- Bridge spans at South Assembly Area
- Steel delivered for spans
- Bridge spans for Tracks 2 & 4 under construction
- Steel arrives for bridge spans
- Footings excavated at South Assembly Area
- South Assembly Area
- South Assembly Area
- Forming up the footings at South Assembly Area
- South Assembly Area Bridge Footings April 3, 2019
- Rebar for footings South Assembly Area
- South Assembly Area
- Trusses arrive at South Assembly Area
- Decks ready for transport
- Two deck spans ready
- Concrete poured on spans
- Formwork at North Assembly Area
- Formwork on North Assembly Area Spans
- Bridge Spans and Formwork at North Assembly Area
- Bridge decks with formwork
- Deck superstructure construction North Assembly Area
- Rebar on deck superstructure
- Girders at North Assembly Area
- Girders form deck superstructure
- North Assembly Area Footings and Trusses
- Temporary abutment at North Assembly Area
- Footings poured and temporary abutments at North Assembly Area
- North Assembly Area with footings and trusses
- Installing re-bar for bridge deck construction
- Footings for bridge superstructure at North Assembly Area
- Soil nailing in progress at North Assembly Area.
- Stripping Top Soil in North Assembly Area July 2018
- Clearing and Grubbing S. State Street at Elm
- Removing Top Soil North Assembly Area
- North Assembly Area
- North Assembly Area
- Excavation at North Assembly Area
- Four deck spans under construction at North Assembly Area
- Caps beams on falsework at North Assembly Area
- Cap beams atop falsework at North Assembly Area
- Girders arrive at North Assembly Area
- Train crossing West Side jump span on Track 4
- Train crossing at jump span, west side Track 4
- Excavation under tracks, Oct. 2018
- Excavation under tracks, East side, Oct. 2018
- Excavation under tracks, west side, October 2018
- Lagging under West side jump span
- Walers and struts under jump span
- Excavation under Tracks 4 & 2, West Side
- Train tracks line the new jump span.
- Track 3 during jump span installation
- West span welding, Track 4, Sept. 2018
- Track 4 west jump span delivery Aug. 2019
- Jump spans are lifted into place.
- Track 1 outage to install jump spans, Sept. 2018
- Work taking place on Track 5 for jump span installation.
- Track 3 Jump Span Install
- Metro North running trains on Track 4
- Metro North continues service during jump span installation
- Micro-piles staged in construction area
- Micro pile casings await installation for the new bridge abutments.
- Micro-piles will be installed to support the new bridge abutments
- Jump spans await installation
- Original iron girders under Atlantic Street Bridge
- Track shadows on Atlantic Street
- Pre-Construction of Jump Spans
- Pre-construction of jump spans, taken April 2018
- Existing Atlantic Street Bridge under tracks
- Fascia Reveal RW 106
- Fascia Reveal RW 106
- Retaining Wall Fascia Reveal
- Retaining Wall 106 April 3, 2019
- Concrete Pour RW 106
- Retaining Wall Continued Concrete Pours
- Monopole #991 Night Work
- Monopole #991 Drill rig
- Stair A Wall 105
- Pre-cast concrete panels form retaining wall
- Retaining Wall with Lagging
- Retaining Wall lagging Wall 106
- Pre-cast concrete lagging forms the new retaining wall.
- H-piles rise high for supporting the new retaining wall on S. State Street.
- H Piles Wall 106
- H Piles Wall 105
- Drill Rig on S. State Street at Wall 106
- Pile driving along Wall 106 for new retaining wall
- Steel H-piles await installation along S. State Street
- H-piles are mobilized pre-installation in the drilled shafts
- Center Pier Micro Piles Underway
- Center Pier excavation
- Center Pier excavation
- Center Pier pile drilling
- Drilling piles for Center Pier
- Center Pier SOE Piles
- Center Pier Excavation April 3, 2019
- Center Pier excavation advances
- Pedestrian bridge girders in place at the new Atlantic Street Bridge.
- Pedestrian girders installed
- North side of Atlantic Street Bridge before girder installation
- North side of bridge before girder installation
- Formwork on western abutment, north side of bridge
- North side of bridge before pedestrian girders installed
- Form work on abutment prior to girder installation
- Formwork on abutment prior to girder installation
- Concrete poured for completed abutment on North Side of bridge
- Foundations for new Track #7 platform
- South side of Atlantic Street Bridge
- South side of Atlantic Street Bridge
- South side of Atlantic Street Bridge